A privately held developer and operator of energy generation and storage facilities across California. Forty years on the grid — designing, permitting, building, and dispatching the capacity a renewables-heavy system depends on.
Six disciplines under one roof — development, permitting, construction, operations, maintenance, and research.
Fast-start peaking and reliability generation, 45–98 MW class, sub-10-minute starts. Engineered for grid stability in a renewables-heavy mix.
Enhanced Gas Turbine architecture — gas turbines and battery storage dispatched as one asset. ~60% reduction in start emissions.
Standalone BESS and co-located solar from greenfield through commercial operation, interconnection, and dispatch optimization.
CEC, AFC, CPUC, SCAQMD, SDAPCD, SJVAPCD. Twelve filings since 1982 — every one reached commercial operation.
In-house operations across the fleet, manned 24/7. The same engineering team from design through thirty years of operation.
First commercial integrated hybrid gas-battery facility in the U.S. Active research in hydrogen blending and long-duration storage.
Eight operating facilities across three California air districts. Every megawatt developed by Wellhead is still operated by Wellhead.
| Unit | Facility | Location | Type | COD | Capacity | Status |
|---|---|---|---|---|---|---|
| U-01 | Stanton Energy Reliability Center | Orange Co. | Hybrid EGT | 2020 | 98 MW | Online |
| U-02 | Stanton Battery Energy Storage | Orange Co. | BESS | 2020 | 26 MW | Online |
| U-03 | Chula Vista Energy Center | San Diego Co. | Peaker | 2009 | 45 MW | Online |
| U-04 | El Cajon Energy Center | San Diego Co. | Peaker | 2017 | 45 MW | Online |
| U-05 | Escondido Energy Center | San Diego Co. | Peaker | 2009 | 45 MW | Online |
| U-06 | Delano Energy Center | Kern Co. | Cogen | 2010 | 49 MW | Online |
| U-07 | Yuba City Cogeneration | Sutter Co. | Cogen | 1989 | 44 MW | Online |
| U-08 | Fresno Cogeneration Partners | Fresno Co. | Cogen | 1988 | 57 MW | Online |
Selected recognition for engineering, emissions performance, and innovation in dispatchable hybrid operation.
The team that develops the asset is the team that permits it, builds it, and operates it for the next thirty years. Continuity is the product.
Start a conversation